Columbus Creek January 2024

Project Update

Horizontal Construction is complete (Grading 95%, Storm 100%, Sewer 100% and Water 100%) for Columbus Creek. The curb is installed and throats and tops are mostly complete. Binder is down and site contractor is looking to turnover the site to the vertical GC . Subdivision Plat has been approved and each building has its own address.

Progress Video